Five practical strategies for investigating existing buildings
Authored by SK&A Project Manager Naina Bhanot, EIT, LEED AP
Renovation and adaptive reuse projects often begin with a simple question: Are the existing structural drawings available?
When the answer is no, the discussion can quickly move toward contingency, risk, and worst-case assumptions. But the absence of drawings is not, by itself, a structural conclusion. It is the starting point for a defined investigation.
The drawings were only ever a description of the structure. The building itself remains in place. Its framing, foundations, materials, repairs, cracking, settlement, and deflection provide direct evidence of how it was built and how it has performed under load.
A missing drawing set does not define what can be known about a building. It simply defines the work required to know it.
The engineer’s task is to collect that evidence in a disciplined sequence, test the assumptions that matter, and develop a reliable basis for design. The process will vary with the building’s age, construction type, condition, accessibility, and proposed use. In practice, however, five key strategies consistently address the central questions: How is the building framed? What records survive? What supports it below grade? What is it made of? And what design assumptions governed its original construction?

1. Records Research – Following the Paper Trail
“No drawings exist” often means that the first search did not find them. Records research is usually a low-cost step and should precede intrusive work.
The search should begin inside the building. Engineer’s room, facilities offices, mechanical-room storage, old flat files, and archived tenant fit-out packages may contain original blueprints, structural sheets reproduced in later submissions, or fabricator erection drawings. Long-term facilities staff may also know where leaks occurred, which floors vibrate, what repairs were made, and which areas have repeatedly caused concern.
If records are found, they should be treated as evidence of design intent, not automatic confirmation of as-built conditions. Representative beam depths, column sizes, slab thicknesses, and bay dimensions still need to be checked in the field.
The search can then expand to municipal permit archives, the original architect or engineer, prior owners, property managers, historic preservation offices, university collections, insurers, and fabricators. Even a partial drawing set can materially reduce the investigation scope in a repetitive building.
2. Field Observation – Listening to the Structure
A building that has remained in service for decades has effectively undergone a long-term load test. Field observation is how the engineer records and interprets the results.
A brief walkthrough is not a structural survey. A useful investigation requires access, measurement tools, photographs, field sketches, and permission to open finishes where framing is concealed. Crawlspaces, attics, roofs, mechanical penthouses, and the spaces above suspended ceilings often provide the clearest view of the structural system.
The first visit should focus on documentation rather than early conclusions. Bay dimensions, member depths, joist spacing, wall thicknesses, bearing conditions, and changes in floor elevation should be recorded consistently. Inaccessible areas should be documented as unknowns because they establish the scope of the next phase.
Fieldwork also reveals conditions that would not necessarily appear on an original drawing set: notched members, infilled openings, abandoned shoring, altered framing, localized repairs, or slab openings added during later renovations.
At one of the recent SK&A projects, drawings recovered from a building engineer’s room indicated slab openings which were observed in the field to be infilled. Field observation on the same project indicated an archaic floor system which had to be researched before designing around it.
The load path must then be traced. Where framing is exposed, follow the gravity and lateral systems through the building and down to the foundations. Misaligned columns, joists bearing on partitions, unexplained transfer conditions, and the absence of a recognizable lateral system are not details to resolve later. They are signals that targeted verification is required before analysis proceeds.
Observe deformations and signs of distress. Crack patterns, deflection, corrosion, spalling, decay, and efflorescence help identify where the structure has been affected by movement, demand, or water. A review of past and proposed occupancy is equally important.
3. Below-grade Investigation – Verifying the Foundation
Foundations are typically the least accessible parts of an existing building and the most expensive to remediate if evaluated incorrectly.
Strategically located test pits provide direct confirmation of foundation type, dimensions, bearing depth, material condition, and visible reinforcement. Locations should be selected to answer specific questions: the most heavily loaded column, an area receiving new demand, a location with settlement-related distress, or a representative condition that can calibrate assumptions elsewhere.
Non-destructive methods can help locate foundations and reinforcement and can improve the selection of test-pit locations. They support physical verification, but they do not eliminate the need to expose critical conditions where the design depends on them.
Foundation capacity also depends on the soil beneath it. Early coordination with the geotechnical engineer is therefore essential. Borings, test pits, or in-place testing at the bearing elevation can establish soil classification, density, groundwater conditions, and a defensible basis for allowable bearing pressure.
Service history matters, but it must be used carefully. A footing that has carried its existing load for decades without measurable settlement provides useful evidence of past performance. It does not, by itself, justify new load. Where demand increases, capacity should be verified.
4. Targeted material testing – Replacing assumptions with data
Unverified material properties can produce two different problems: an unconservative design or unnecessary strengthening. A targeted testing program should resolve the unknowns that control the evaluation, rather than collect data without a clear design purpose.
For structural steel, coupon testing can establish yield strength, tensile strength, and elongation. Chemical analysis is particularly important where welding to existing steel is proposed because older steel may not have the weldability assumed for modern material. Existing rivets, bolts, and connection details also need to be identified and evaluated as part of the system.
The same principle applies to concrete, masonry, and timber. Concrete cores and reinforcement scanning can establish strength, bar arrangement, cover, and material condition. Masonry testing can support assumptions for compressive and shear capacity and can distinguish mortar types that require different repair approaches. Timber investigation may include species identification, visual grading, and inspection for decay, insect damage, splits, and notching.
The governing standard will determine the required knowledge level and the permitted use of default values. In practical terms, a modest, well-designed testing program can prevent a much larger strengthening scope based on unnecessarily conservative assumptions.
5. Historical Research – Understanding the Building’s Era
Older buildings often contain structural systems and materials that are no longer common in current design practice. Correctly identifying the system is essential because its behavior, detailing, and characteristic vulnerabilities may differ substantially from modern construction.
Depending on the period and region, an existing building may include cast iron columns, wrought iron beams, load-bearing masonry, heavy timber, riveted steel, terra cotta floor systems, hollow clay tile, cinder concrete, proprietary reinforcement, gypsum roof decks, open-web joists, precast plank, or post-tensioned slabs. Some of these systems require extreme caution during investigation, especially before cutting, coring, or assigning load paths.
Historic building codes, engineering handbooks, manufacturers’ catalogs, historic steel-shape data, preservation guidance, and colleagues with direct experience are all useful sources. The goal is to understand the design basis, material assumptions, detailing conventions, and failure modes that shaped the building.
A structure designed under an earlier code reflects the loads, allowable stresses, and lateral-force provisions of that time. That context helps the engineer identify where reserve capacity may exist and where deficiencies are more likely. Unexpected field findings should be researched before the design is developed around them.
From unknown conditions to a defined engineering scope
In conclusion, the absence of existing structural drawings should lead to a structured investigation rather than an assumption that the building cannot be reliably evaluated. Field observation, records research, below-grade investigation, targeted material testing, and historical research form a practical sequence. Each step narrows the unknowns and provides a firmer basis for the next decision.
These strategies do not replace the knowledge requirements established by the applicable codes and evaluation standards. They are how the project team develops that knowledge in a form that can support analysis, design, and construction.
The process also improves project planning. When structural engineering is engaged early, missing information can be converted into a defined scope that is coordinated, scheduled, and budgeted before construction. The result is not merely a substitute for lost drawings. It is a verified record of the structure as it exists today, often including modifications and conditions that the original documents would never have captured.
When supported by careful investigation, proper analysis, engineering judgement, and coordinated sequencing, an existing building without record drawings can be understood with confidence and adapted for its next service life.